Distorted Bay Window With Ornate Terracotta Blockwork

Structural Repairs for Bay Window with Ornate Terracotta Blocks

cracks bay period terracotta - Distorted Bay Window With Ornate Terracotta Blockwork

The exterior of this Victorian/Edwardian property in the London Borough of Lewisham, SW13, has a number of beautiful period features.  The ground floor bay window columns have ornate capitals, the bay window brickwork includes terracotta blocks below the 1st floor bay and the roofline has decorative terracotta blockwork below the eaves.

In common with many properties of this age, a combination of ageing and ineffective restraining of the bay window columns, together with de-bonding of the main elevational brickwork, was allowing the bay window to lean outward. This was also opening up large cracks in the surrounding brickwork. Without structural repairs to restrain and reinforce the masonry, it will fail and lead to the collapse of the structure above.

debonded brickwork bulges 1.3 - Distorted Bay Window With Ornate Terracotta Blockwork

Read our frequently asked questions about bay window structural repairs.

The Structural Problem

This period home in Inner London was at risk of structural collapse. Protecting the fragile terracotta blocks and eave brackets was a key consideration in designing the structural repair plan.

terracotta blocks eave brackets - Distorted Bay Window With Ornate Terracotta Blockwork

Some of the structural problems included:

  • Large cracks around the bay window
  • Clearly visible outward leaning of the first floor bay window masonry columns and lintels
  • Significant outward movement of the masonry lintel to the left side main elevational wall
  • Significant movement of all the terracotta ornate blocks below the soffits
  • Fragile, period terracotta blocks & knee braces (eave brackets) required delicate handling

 

leaning bay window gaps - Distorted Bay Window With Ornate Terracotta Blockwork

AWT’s repairs were designed to target the root cause of the structural failings. Due to AWT’s specialist knowledge and equipment, demolishing and rebuilding the bay window was not required.  AWT used bespoke drilling jigs to install fixings within the masonry to restore structural integrity without damage to the period features, especially the fragile terracotta blocks.

The Structural Repair Solution

AWT’s specialist structural repair tools allow the masonry to be gently moved back to its correct alignment. As shown in the photo below, custom-made drilling equipment allows the installation of fixings within the masonry with minimal impact on the facade of the property. This redistributes the upper-storey loads and restrains the brickwork to prevent cracking and bulging. AWT’s specialist repairs were designed to realign and restore the masonry without damaging or replacing the fragile terracotta blocks.

restoration terracotta block bay window - Distorted Bay Window With Ornate Terracotta Blockwork

The first step was to bring the masonry back in line by:

  • Installation of temporary supports
  • Intrusive inspection of masonry components that appear to be of solid masonry sections but could be nominal thickness components backed with timber framework, amending repair plan as necessary
  • Careful removal of dislodged ornate terracotta blockwork and knees (aka knee braces or eave brackets)
  • Set up AWT designed realigning cramping equipment
  • Deployment of specialist hydraulic jacks to realign the bay window masonry and elevational brickwork

The structure of the property was then strengthened by the installation of high quality specialist fixings:

  • Long diamond drilled grouted ties
  • Lateral restraints
  • Grout injection ties
  • Resin bonded ties

Finally, the finishing touches were added to restore the period beauty of the property:

  • Reinstate the terracotta ornate blockwork
  • Repair masonry pillars and cills with Monolevel FC anti-carbonation cosmetic grade mortar
  • Replace cracked bricks and mortar ensuring a suitable colour match

The repaired masonry elements were left ready for repainting. No external fixings were required – leaving the period features of the property to be enjoyed for years to come.

masonry brickwork repairs inner london - Distorted Bay Window With Ornate Terracotta Blockwork

Action Wall Ties are specialist structural repair contractors with the skills required to realign and strengthen leaning bay window masonry including period and heritage properties with fragile or ornate features of brickwork, terracotta stone/masonry elements and plaster stucco works. AWT work along with property owners, architects, project managers and local authorities on large and small projects.

AWT are available in Kent, London, Essex, Surrey and Sussex. To arrange a survey or to discuss project details, please use our contact form, email us or call us on 01227 721 255.

Grade 2 Listed Gable Stabilisation in SW London

simple horizontal - Grade 2 Listed Gable Stabilisation in SW London
geograph 3281453 by David Anstiss - Grade 2 Listed Gable Stabilisation in SW London
Dutch gable ornate - Grade 2 Listed Gable Stabilisation in SW London
gable repair plans 2 - Grade 2 Listed Gable Stabilisation in SW London
listed building stone repairs - Grade 2 Listed Gable Stabilisation in SW London
ornate gable repairs - Grade 2 Listed Gable Stabilisation in SW London
Grade II Listed Dutch Gable Repairs
Ornate Stone Dutch Gable Repairs
Structural Repairs for Grade II Gable
Structural Repairs for Victorian Dutch Gable
Victorian Gable Wall Repairs
 
simple horizontal - Grade 2 Listed Gable Stabilisation in SW London

Repairs to Failing Grade II Dutch Gables

Kingsway Square in Battersea, South West London is a Grade II listed building, formerly known as Mountfield Mansions, it formed part of Westminster College. Designed by E. W. Mountford in the late 1800s, it is an impressive building packed with architectural details.

The Victorian era Dutch gables, composed of red brick and ornate stonework were structurally unsafe and at risk of collapse. A sympathetic structural repair solution was required that could restore structural integrity without compromising the beauty of the facade.

The Structural Problem

Inspection of the Dutch gables walls that feature in this grade 2 listed building revealed that they had failed structurally. The masonry could be manually rocked and was leaning and at risk of collapse. Cracks were evident in the gable masonry and stonework. The masonry of the gable walls required urgent realignment and strengthening.

Traditional building methods would require deconstruction and rebuilding each gable wall. This would obviously have entailed substantial inconvenience to the residents as well as additional costs for internal redecoration. A cost-effective, long-term structural repair was required.

Due to internal concerns, one of the residents also required a tailor-made solution that used exterior steel fixings.

As with many buildings that AWT is called in to repair, there was evidence of previous structural repairs. Patress/anchor plates were visible on the brickwork but they had failed to address the root causes of the unstable gable masonry.

The Structural Repair Solution

AWT provided a bespoke structural repair solution to reinforce the gable walls. AWT’s unique skill set and proven experience were invaluable on such a delicate project.

The consulting structural engineers recommended the most appropriate remedial solution would be to install Cintec anchors vertically through the top of the stone and extending at least as far below the rafter line as the stonework extends above it.

A custom diamond drilling rig was required to allow precision drilling through over 3m of stone and brickwork at the apex of the gables. The Cintec sock anchors were then installed.

Cintech sock anchors consist of a stainless steel rod in a mesh sleeve. The anchor is installed deep into the masonry by the use of precision drilling techniques. The sleeve is then filled with a specially designed cementitious grout. This provides a mechanical and chemical bond between the masonry and the anchor that restores structural strength. The small diameter drill holes required for Cintech sock anchors are filled with color-matched mortar to provide a virtually invisible repair.

In contrast to long, drawn-out rebuilding work, Cintech sock anchors provide a highly efficient repair method. This technology also removes the need to use visible fixings such as pattress/anchor plates.

Four lateral restraints were also installed on each side of the gables to restore structural integrity and restrain the masonry. These stainless steel lateral restraints screw directly into the timber rafters and are resin bonded to the masonry to provide a long-lasting structural reinforcement of the gable walls.

Special Request Alternative Repair Solution

For the resident that requested exterior steel fixings a bespoke, Y-shaped frame was fabricated. This was fitted out of sight, to the rear of the gable masonry, ensuring it did not interfere with the lightning conductors on the gable.

The AWT team carefully cut away the protruding moulding at the rear of the gable to provide a flat surface. The bracket was then fixed in place with stainless steel resin bonded fixings. The finished repair provided a long-term structural repair without compromising the beauty of the Victorian gable masonry.

AWT provides cost-effective structural repairs for a wide range of structural issues. Our specialist repair techniques make us the ideal choice for projects involving listed and heritage buildings. 

We work together with structural engineers, architects and project managers to find economical and effective solutions. We operate not only in London but across the whole of the South East of England.

To book a time for one of our surveyors to visit your property or to discuss your requirements, call us today on 01227 721255, email us at enquiries@actionwallties.co.uk or use our contact form to get in touch.

Remedial Wall Ties for Victorian Semi in Surrey

Bulging & Cracking Brickwork Across Front of Victorian Semi Detached Houses

These 2 Victorian semi detached houses in Egham, Surrey had a significant bulge in the brickwork above the first floor windows. There was also a failing brick arch lintel and cracking to the brickwork. Without swift action the masonry would collapse.

AWT were called in to repair the defects and allow the homeowners to avoid slow, expensive and disruptive rebuilding work. Equipment designed by AWT was used to realign the brickwork, stabilise and reinforce the masonry and then install new wall ties and lateral restraints.

Surrey bowing masonry repairs - Remedial Wall Ties for Victorian Semi in Surrey

The Structural Problem

The AWT survey team visited the property in Surrey, TW20 to identify the root cause of the visible bulging of the masonry at the front of the property. The AWT survey team quickly identified that this Victorian semi was built using cavity wall construction and that failing cavity wall ties were likely a root cause of the problem.

A limited inspection of the wall ties was undertaken by drilling 12mm holes in the outer leaf of brickwork to view within the cavity via an endoscope. This confirmed the diagnosis of failing wall ties, as can be seen from the photos taken with the endoscope, as the corrosion of the metal was clearly visible. The mild steel ties were all in a similarly heavily corroded condition and showing signs of de-laminating.

Failing Victorian wall ties surrey - Remedial Wall Ties for Victorian Semi in Surrey

Horizontal cracking, lifting and opening up of joints was noted at irregular intervals on the front elevation. Metal ties were located behind the cracks, with an electronic wall tie locator.

Corrosion of the embedded mild steel wall ties was causing them to expand to many times their original size. This was damaging the outer leaf of brickwork, splitting the bed joints and causing either lifting or bowing of the walls and damage to internal finishes. This left the wall vulnerable to vertical and wind loads, especially such a large gable wall.

Without structural repairs the wall would continue to bow further and eventually collapse. Traditional building methods would have required the partial deconstruction and rebuilding of the front of the properties.

The Structural Repair Solution

Completed wall tie repairs Surrey - Remedial Wall Ties for Victorian Semi in Surrey

Unlike some cavity wall tie repair contractors, AWT always works to the standards laid out in the Building Research Establishment Specification Digest. This means that the separation between new wall ties, the layout pattern of the new wall ties and the material used to manufacture the new wall ties all meet the highest standards to ensure a safe, long term structural repair.

To avoid failure of the brickwork and brickwork arch AWT realigned the bulged brickwork, installed new stainless steel wall ties, isolated the old ties to prevent them causing further damage and formed a composite beam within the external brickwork. The formation of deep masonry beams within the existing masonry supports the masonry and maintains the integrity of the brickwork.

AWT use their own custom designed hydraulic realignment equipment and diamond bladed precision drilling rigs. This allows the new fixings to be installed with minimal disturbance to the masonry. A variety of specialist fixings were introduced into the brickwork to restore the strength and stability of the wall.

As can be seen in the photo above, when the work is complete there are no visible fixing either inside or outside the property. The AWT team also take the time to colour match any replacement bricks as well as matching the colour, texture and pointing style of the mortar where work has taken place.

AWT provide cost effective structural repairs for a wide range of structural faults including failing cavity wall ties and bulging brickwork. We operate not only in Surrey but across the whole of London and the South East of England.

To book a time for one of our surveyors to visit your property or to discuss your requirements, call us today on 01227 721255, email us at enquiries@actionwallties.co.uk or use our contact form to get in touch.

Bulging Gable Wall in NE London

Bulging End of Terrace Gable Wall

The owners of this Victorian / Edwardian end of terrace home in the Redbridge area of North East London called in AWT because of the significant outward bulging of the large gable wall of their property. There was also cracking to the internal gable end walls as well as to the internal party wall between the property and its neighbour.

The Structural Problem

The AWT survey team visited the property in Woodford Green to identify the root cause of the visible bulging movement of the large, solid brickwork flank/gable wall. Due to aging, ineffective and inadequate restraining of the brickwork the entire gable wall was de-bonding and disconnecting with the rest of the masonry. This was leading to additional problems with the internal beams losing support.

debonded brickwork bulges 1.3 - Bulging Gable Wall in NE London

Without structural repairs, the large gable wall would continue to pull away and eventually collapse. Traditional building methods would have required the partial deconstruction and rebuilding of the flank wall. Even then, it would not have solved the root cause of the problem – inadequate restraining of the gable wall.

The Structural Repair Solution

The team at AWT designed a structural repair package that would bring the brickwork back into alignment and add tensile strength to the structure. The specialist tools and fixings used by AWT enable them to restore the brickwork’s integrity without visible fixings or rebuilding work.

Bed joint reinforcement beaming, grout tie injection and lateral restraints were employed to reinstate the uniformity of the wall and provide restraint. The formation of continuous beams within the existing masonry redistributed the upper storey loads while at the same time assisting in restraining diagonal cracking and bulging tendencies.

A specialist drilling rig, designed by AWT, was used to drill through the brickwork at a shallow angle to maximise the number of bricks connected by each helical, grout bonded fixing. The internal timber beams were reconnected to the masonry using resin bonded stainless steel fixings.

Cracked and disturbed areas of mortar were raked out and replaced with fresh mortar that was matched for colour, texture and pointing style.

AWT provided a long term solution for the bowing gable brickwork. By targeting the repairs exactly where they were required the work was completed swiftly and with minimum inconvenience to the residents. The hidden fixings used by AWT preserved the beauty of the old yellow stock brickwork.

Action Wall Ties are structural repair contractors with the specialist skills required to reinforce and repair large areas of bowing and bulging brickwork. AWT work along with property owners, architects, project managers and local authorities on large and small projects.

AWT are available in Kent, London, Essex, Surrey and Sussex. To arrange a survey or to discuss project details, please use our contact form, email us or call us on 01227 721 255.

Hazardous Masonry on Grade 2 Listed Building

Listed Building with Bulging & Cracking Masonry

This Grade II listed building in Thanet, Kent, was built in the 1840’s. The owners of this period property were facing the prospect of demolition and rebuilding of the facade of the property due to serious structural defects. Previous repairs using standard building techniques had failed to solve the structural problems. The property is currently in use as a nursery school. The business would have been forced to close for several months during traditional building works. AWT were able to repair the severe structural problems in a couple of weeks and preserve the period features without disrupting the running of the business.

Thanet grade 2 listed - Hazardous Masonry on Grade 2 Listed Building

The Structural Problem

The structural issues with this Victorian, Grade 2 listed property in Ramsgate, Kent were becoming hazardous due to the risk of falling masonry. Traditional building methods would have required several months of expensive and messy deconstruction and rebuilding work. The business would have been forced to close during the building works and the subsequent re-plastering and redecoration.

The front of the building had clearly visible bulging and cracking to the head of all the first floor windows. There were also cracks in the brickwork and stucco works each side and to the underside soffit of the window opening heads. There were clear signs of previous attempts at repairs that had failed to get to the root cause of the problems.

grade 2 listed structural defect - Hazardous Masonry on Grade 2 Listed Building
Buckling Brickwork

As shown in the photo below, the mild steel embedded within the masonry had corroded and the rust caused it to expand to several times the thickness of the original metal. The heavily corroded wrought iron arch bars were lifting and cracking the brickwork and the decorative stucco around the windows. The stucco stringer course frieze and cornice of the parapet wall was also cracking and distorting. Previous attempts at repairs had provided a temporary, cosmetic repair but had failed to solve the underlying structural defects.

The continued expansive corrosion of the wrought iron arch bars would, without remedial works, lead to the failure of the masonry and the risk of detached masonry falling from the building. Urgent structural repairs were required.

The Structural Repair Solution

Structural repairs to listed buildings need to be handled carefully to preserve the period features of the building. AWT have many years of experience working on listed properties. AWT can help the owners of listed buildings to navigate through the process of obtaining permission for repair works.

The specialist tools and techniques that AWT employ allow structural repairs to be made without the need for visible fixings. Using custom designed drilling and cutting tools, AWT can remove corroded metal fixings and embed new stainless steel fixings within the masonry.

Scaffolding listed building repairs - Hazardous Masonry on Grade 2 Listed Building

In order to allow the business to remain open during the structural repair works, AWT arranged for the scaffolding to be erected at the weekend while the nursery was closed. The scaffolding was then double boarded and netted for safety. The AWT crew accessed the scaffolding from the side of the building allowing parents, children and staff to access the building as usual through the main entrance.

 

The AWT team used their specialist techniques to form composite beams within the existing brickwork and then remove and replace the corroded wrought iron arch bars. The team then reconnected and reinforced the brickwork above the windows and the parapet wall. They also repaired the cracked decorative stucco.

This project required a combination of:

  • Bed joint reinforcement beaming
  • Grout tie injection
  • Resin bonded ties
  • Cintec sock anchors
  • Removal of corroded mild steel arch bars
  • Replacement arch bars
  • Brickwork repairs

The team at AWT strive to make all works as sympathetic as possible with the existing masonry. Not only do they try to match replacement bricks and pointing for colour and style they even match the mortar mixture texture.

The high quality fixings used by AWT combined with their thorough knowledge of structural defects ensures a long term solution to structural issues.

Action Wall Ties are structural repair contractors with the specialist skills required for listed buildings. AWT work along with property owners, architects, project managers and local authorities to preserve historic buildings.

AWT are available for large and small projects in Kent, London, Essex, Surrey and Sussex. To arrange a survey or to discuss project details, please use our contact form, email us or call us on 01227 721 255.

Failing Bay During Window Replacement

Bay Window Repairs During Fitting of New Windows

This period property in Southfields, South West London had failing bay window masonry. The old sash windows had been removed but fitting of the new windows revealed the bay window was unstable and out of alignment. Without professional structural repairs this would result in the collapse of the bay window masonry.

SW London Bay Repairs - Failing Bay During Window Replacement

The Structural Problem

As with many Victorian/Edwardian properties, issues with the bay windows became apparent during the fitting of replacement windows. New box sash windows were being installed but the surrounding masonry was clearly out of alignment. Repairs were necessary before the replacement window work could be fully completed.

This property in London, SW18, had visible cracking and dropping to the front bay window masonry. The bay had lost the internal brickwork support during the removal of the old box sash windows. Cracking of the first floor masonry lintel components and rendered brickwork were clearly visible. The original internal supports at the head of the bay window structure had been removed together with the original box sash windows.

The combination of inadequate restraining, ageing and the removal of the structural supports to the first floor during the replacement of the original window frames left the bay window unstable. Without suitable structural repairs the bay window was in danger of collapse.

The Structural Repair Solution

To reinstate stability, the bay window structure required the internal supports to be reinstated plus reinforcement of the masonry. Temporary supports were installed to the underside of the first floor front bay window masonry lintel. All the debris was removed from the crack and the lintel was lifted into a more level line with the adjacent brickwork.

 

Bed joint reinforcement beaming, grout tie injection, resin bonded ties, steel lintels and columns and some masonry repairs were all required. The formation of continuous beams within the existing masonry redistributed the upper storey loads to the supporting structure below while also assisting in restraining diagonal cracking and bulging tendencies. A bespoke steel box lintel frame supported on steel box columns was also fixed to the inside of the masonry columns.

The specialist techniques used by Action Wall Ties installed all the stainless steel fixings within the masonry leaving no visible fixings. Once the area had been redecorated the bay window looked as good as new.

AWT provide cost effective structural repairs for a wide range of structural faults including bay window reinforcement, realignment and lintel repairs. We operate not only in SW London but across the whole of London and the South East of England.

Read our frequently asked questions about bay window structural repairs.

To book a time for one of our surveyors to visit your property or to discuss your requirements, call us today on 01227 721255, email us at enquiries@actionwallties.co.uk or use our contact form to get in touch.

Bowing Pebble Dash Gable Wall

Pebble Dashed Bowing Gable Wall

AWT was called in to investigate a bulging gable wall and cracked ceilings at the end of a terrace in Walthamstow, East London. A structural repair solution was needed that would not require the removal of the Spar pebble dash render.

London E17 Bowing gable wall - Bowing Pebble Dash Gable Wall

The Structural Problems

The homeowner called in AWT due to cracking in the internal walls and ceilings near the gable wall in this terraced home in London E17. Significant external outward bulging of the gable wall was also visible.

Gable wall problems are common in properties of this age and type. Ineffective and inadequate restraining of the gable masonry combined with ageing allows the gable brickwork to bulge and bow outwards.

A cost-effective solution was required that would restore the structural integrity, if possible without the need to remove the Spar pebble dash render from the gable wall.

If structural repairs are sought early enough, as in this case, AWTs specialist repair techniques may allow for repairs without removing the render/pebble dash. The small disturbed areas of render/pebble dash can then be made good with a concrete repair mortar system.

Standard building methods would require at least partial removal of the render and then re-rendering afterwards. Removal of the pebble dash render would have added to the expense and inconvenience for the householder. The access to the gable wall was also less than ideal.

The Structural Repair Solution

London E17 Bowing gable repairs - Bowing Pebble Dash Gable Wall
Location of Fixings

AWT used precision drilling techniques to embed fixings within the masonry with the minimum disturbance to the pebble dash finish.

Bed Joint Reinforcement Beaming: As shown by the red dotted line, stainless steel fixings were introduced into the masonry to form a deep masonry beam that redistributed the load from the upper storey and restored structural strength.

Grouted Tie Injection: As shown by the green lines, precision drilling techniques were used to install helical, stainless steel, grouted ties to restrain the gable brickwork.

Lateral Restraints: As indicated in yellow, stainless steel, resin bonded restraints were fitted to tie the gable wall masonry to the timber joists. This further restrained any tendency for the brickwork to bow outwards.

Re-pointing Disturbed Areas: AWT colour matches the mortar that is used to re-point disturbed areas and drill holes.

As can be seen from the after photo, the structural repairs to the bowing gable are barely visible. The pebble dash rendering remains intact and the underlying structural defects have been dealt with in a cost effective manner.

For fast, effective solutions to bowing gable walls and other structural problems contact AWT today. AWT can advise on structural repairs to properties with render, pebble dash and spar dash. We provide professional solutions to a wide variety of structural issues for homeowners across London, Kent, Surrey and Sussex. Contact us on 01227 721 255, or email us.

Stone Arch & Bay Window Reinforcement

Reinforcement and Repair of Ornate Stone Arch & Bay

This end of terrace home in Walthamstow, East London had 2 structural issues. The stone entrance arch had significant cracking to the brickwork above and cracking in the internal walls. The ornate bay window was dropping and leaning outwards plus the stonework was cracking and spalling.

Walthamstow bay repairs  - Stone Arch & Bay Window Reinforcement

The Structural Problem

The period decorative features on this home in London, E17, were showing their age due to structural issues causing cracked brickwork and stonework. The structural movement had exacerbated the deterioration of the paintwork leaving the beautiful, ornate stonework looking shabby.

There was significant cracking above the stone entrance arch in both the external brickwork and the internal walls.

E17 stone arch repair - Stone Arch & Bay Window Reinforcement

The bay window had visibly shifted and caused cracks in the external brickwork as well as in the interior walls. The supporting columns and cills had become distorted.

These are common problems in such Victorian / Edwardian properties and are usually the result of ageing and inadequate restraining in the original building methods.

The AWT team also had to be prepared in case the masonry components weren’t solid masonry but simply a thin facade covering a timber frame.

 

The Structural Repair Solution

  • Installation of temporary supports & AWT designed cramping equipment
  • Realignment of masonry with hydraulic jacks
  • Precision diamond drilling & installation of stainless steel corded joint reinforcement.
  • Reconnecting the bay window brickwork to the main elevation by embedding grouted 8mm helical bars.
  • Installation of lateral restaints.
  • Repair damaged stonework with Flexcrete Monomix concrete repair mortar system.
  • Crack stitching work to cracked brickwork.
  • Cutting back damaged brick faces or resurfacing damaged bricks where possible using AWT methods.
  • Cutting out badly cracked bricks and replacing with colour matched yellow stock bricks.
  • Re-point disturbed areas with colour matched sand lime and cement mixture.

AWT provided an efficient, cost effective, permanent repair without the need for visible fixings. AWT have the tools and skills to remediate the root cause of these types of period property structural defects. AWT’s specialist fixings meant no rebuilding work was required and so disruption to the homeowner was kept to a minimum. The property was left ready for painting to restore it to its former glory.

E17 bay arch repairs - Stone Arch & Bay Window Reinforcement

Read our frequently asked questions about bay window structural repairs.

For a fast, effective solutions to stone arch and bay window structural problems contact AWT today. We provide professional solutions to a wide variety of structural issues for home owners across London, Kent, Surrey and Sussex. Contact us on 01227 721 255, or email us.

Edwardian Stucco column remediation

London Edwardian Stucco column remediation

Edwardian portico structure with stucco columns cracking and failing – stabilising remediation works involved precision diamond drilling into the edge of the rounded columns directly into the centre of a half brick wall and the injection of grout

case study 56e199f6b5d7f7.59403455 - Edwardian Stucco column remediation

The subject building was a substantial, traditionally-built, elegant Edwardian Stucco finished domestic house in Central London.

This period property required work to remedy cracking and parting of the entrance porch structure without detracting from the look of the property.

Action Wall Ties have highly trained staff with a wealth of experience in dealing with period properties. AWT used their own design of diamond drilling equipment to drill for, and install, ties to strengthen the structure. The property was then made good using special mortars to match the existing finish.

Detailed Case Study

Defect

Cracking to the junctions of the front portico stucco columns with the main elevational walls was reported and noted.

case 7 a - Edwardian Stucco column remediation

case 7 b - Edwardian Stucco column remediation

Discussion

An underpinning scheme was completed, addressing the downward movement leaving the superstructure to be reconnected. Action Wall Ties’ remediation works were designed to assist in restraining the masonry to return the integrity to the structure.

Structural repair solution

The remediation works involved precision diamond drilling into the edge of the rounded columns, directly into the centre of a half brick wall by 1800mm each way to accommodate the injection of grouted ties, reconnecting the columns and walls (as indicated with green lines).

case 7 c - Edwardian Stucco column remediation

case 7 d - Edwardian Stucco column remediation

With the structure stabilised the cracked junctions of the columns with the main elevation were raked out cleaned and injected with cementitious grout, finished and made good with concrete repair mortar.

case 7 e - Edwardian Stucco column remediation

Action Wall Ties have, over many years, developed specialised equipment and methods to facilitate precision diamond drilling in almost any location, into almost any substrate, drilling 20mm diameter holes up to 3 meters long, through to 80mm diameter holes to almost any length, to accommodate the proposed remediation works (i.e. the removal of corroding steel and or installing many types of fixings).

Action Wall Ties have developed methods, and trained skilled experienced operatives, to strive to finish works to be sympathetic with the existing by attempting to match replacement bricks, pointing style and mortar mixture for texture and colour.

Action Wall Ties (AWT) are specialists in masonry reinforcement and repair in London and Kent, providing professional solutions to a wide variety of structural problems. Contact us on 01227 721 255, or email us.

1930s Purpose Built Library

1930s Public Library

A 1930s purpose built library in Welling, near Dartford, Kent. Corroding support angles to the flat brick soldier course lintel required bed joint reinforcement beaming, fenestration lintel repair, grout tie injection and resin bonded ties and removal of the corroding angles.

case study 56e19a7884e823.25433311 - 1930s Purpose Built Library

The subject building was a substantial purpose built library constructed in the mid-1930s of brick on a concrete foundation.

Structural Problems and Issues

Visible cracking and lifting movement noted to the window openings to the top floor front and two side elevations. A total of 20 windows.

The external brickwork soldier course formed a flat arch above the window openings. The flat arches were built on a 50mm × 50mm mild steel angle that was found to be heavily corroding and delaminating.

case 18 a - 1930s Purpose Built Library

Severe corrosion of the embedded mild steel support angles and its resulting expansion had caused severe distress to the adjacent brickwork.

The internal brickwork was being supported by an independent concrete lintel.

Structural Repair Solution

AWT completed a remedial scheme, introducing bed joint reinforcement beaming, fenestration lintel repair, grout tie injection and resin bonded ties.

case 18 b - 1930s Purpose Built Library

1. Bed joint reinforcement beaming:
The introduction of two rows of twin cord reinforcement, forming a composite deep masonry beam – as indicated with red double dotted lines on our proposal images.

case 18 c - 1930s Purpose Built Library

2. Fenestration lintel repair:
To the underside of the fenestration openings head, we drilled for, and injected, grouted 8mm helical stainless steel pins through the brick arch, passing into the line of the composite deep masonry beam installed within the existing masonry – as indicated with green parallel lines on our proposal images.

3. Resin bonded ties:
Within the area of the beaming we drilled for (wherever possible to the centre of a brick), and resin bonded, new 6mm stainless steel remedial ties (four per square metre) above window openings, then re-pointed disturbed areas only with coloured sand and cement mortar.

After the proposed reinforcing works had been completed the windows were removed (by others) to enable the removal of the mild steel angles and making good of the brickwork.

High Quality Structural Repairs

The gallery below shows the completed structural repairs after 15 years. The repairs are as good as new.

Traditional building methods are only able to provide short term, cosmetic repairs. Our skilled structural repair specialists can identify the underlying causes of structural defects and provide long lasting repair solutions.

Councils, housing associations and other public sector organisations across the South East have turned to AWT for cost effective, long term solutions to a wide range of structural issues.

Action Wall Ties (AWT) are specialists in masonry reinforcement and repair across Kent and London, providing professional solutions to a wide variety of structural problems and issues from cracks to wall movement and window sill defects. Contact us on 01227 721 255, or email us.

logo logo logo logo logo logo